Adif is planning a €4.7million overhaul of one of the most problematic tunnels on the Cordoba–Malaga high-speed rail line.
The national railway infrastructure operator said the works on the electrical cabling at Valle de Abdalajis are expected to take two years.
They aim to address recurring electrical faults caused by movements in the tunnel’s structure.
The infrastructure has suffered significant problems linked to underground water pressure, including serious damage to one of its two tunnels in July 2025.
According to Adif’s technical documents, existing electrical cables have suffered repeated breakages and damage to their insulation.
Ground movements and changes in pressure around the drainage systems have contributed to their deterioration, while previous repair efforts have failed to resolve the underlying problem.

Emergency and safety systems
The new electrical network will serve critical infrastructure, including fire protection systems, ventilation, emergency lighting and water pumps.
The project also includes a dual power supply designed to keep essential installations functioning if one supply fails.
The works will cover both tunnels, each measuring approximately 7.3km, which pass beneath the Sierra del Valle de Abdalajis and Sierra de Huma.
Adif hopes the new installations will improve reliability and make future inspections and repairs considerably easier, reducing the need for disruptive maintenance work.
The project has a tender budget of €4.72million, including taxes, and a scheduled construction period of 24 months.